Expansion of the "Teplitsy Ramenskiye" greenhouse
Client: "Teplitsy Ramenskiye" ltd.
The further expansion of the greenhouse complex by 6 Ha with the adjoining industrial block.
The works began in August 2010.
Current status for October 2010:
At the moment, we have finished the foundation installation works, total area 3 Ha, including the industrial block, starting the preparation works for the frame installation.
The works are done by "Rostok" ltd. along with our foreign partner - company Dalsem B.V.
FinishedCurrent
Future